Situation

Cassidy Construction needed to find a way to power the Terex CTL-260 luffing tower crane from a weak grid connection.

16

A

Available on-site power

Grid connection only

7t

CO₂ reduced

per month

265

kVA

Load requirements

Crane + site power

Video poster
0:00 / 0:00
Overview

The grid connection was not large enough to support the crane. Instead of taking the traditional approach and installing a 200kVA generator for the crane, Cassidy chose the CP300 and simply plugged it into their existing temporary site power supply, eliminating the need for a generator all together.

Cassidy are saving money, reducing noise and fumes and are preventing 7 tonnes of CO2 emissions each month.

Project
Auckland Radiology Group
Construction company
Cassidy Construction
Location
Remuera, Auckland, New Zealand
Project start
June 2024
Site loads

Terex CTL-260

Power requirement
150kVA
Input feed
16A three-phase mains supply
Battery system
CP300

Related case studies

Verified