No three-phase,
no problem

Situation

With an 8-storey apartment complex needing to start construction, but the project being held up because of noise restrictions and no access to 3-phase site power, Kalmar Construction was under pressure to find a solution to power their tower crane and the site power.

32A

Available on-site power source

Single-phase mains power

300

kVA

Peak output

all from 32A single-phase

265

kVA

Load requirements

Crane + site power

Overview

The Liebherr 542HC-L Luffing crane, on rent from SMITH Cranes, needed a maximum of 265kVA of peak-power available for the crane, but because the site only had single-phase power available, they believed the E-Gen300 battery system wasn’t going to provide a solution.

After contacting us, SMITH Cranes purchased the E-Gen300, which has both single-phase and 3-phase input charging, and 300kVA of peak-power, making it the perfect solution for this job.

Project
Chelsea Rise
Construction company
Kalmar Construction
Location
Birkenhead, Auckland, New Zealand
Project start
March 2025
Site loads

Liebherr 542HC-L Luffing Crane

Power requirement
265kVA Crane + General site power
Input feed
32A, 230V, single-phase mains supply
Battery system
CP300